06 February 2024
Works continues with the construction of more than 1320 submerged columns. Final unexploaded ordnance search phase to begin

Works proceed rapidly to build the new breakwater, with a new milestone during these days: that of laying 1 million tonnes of gravel along the seabed, offshore from Genoa, reaching 40% of the laying activities. A quantity that allowed building, since May 2023, more than 1,320 submerged gravel columns, concomitantly safeguarding the marine ecosystem. While at the same time, the activities to search for the underwater unexploded ordnances continue to advance, 70% of which have been in fact already completed.