28 April 202620th caisson installed project reaches 900 metres in lengthConstruction of the New Genoa Breakwater continues with the installation of the 20th caisson.
31 March 2026Seventeenth caisson of New Genoa Breakwater installed Production of the protective armour blocks to safeguard the base of the structure has started The construction site of the New Genoa Breakwater marks another significant milestone with the installation of the 17th caisson by the PerGenova Breakwater consortium, led by Webuild, which is doing the project on behalf of the Western...
23 February 202616th caisson of new Genoa Breakwater installed. Construction of superstructure has also begunThe construction site of the New Genoa Breakwater has taken another step forward: the 16th caisson has been laid on the seabed, a concrete structure comparable in size to an eleven-story building.
12 December 202515th caisson installed and more than 50,000 gravel columns completed. Supervising the depths: high-tech monitoring converts seabed into dataThe construction site of the New Genoa Breakwater, one of the most complex maritime works in Europe, is progressing both above and below the water’s surface.
03 December 202514th caisson installed for New Genoa Breakwater, a key project for port’s future86% of material for foundation posed on seabed over 49,000 underwater columns installed