09 June 2026The New Genoa Breakwater passes the first kilometre of development twenty-third caisson installed. The construction site is progressing on multiple fronts at a steady pace, shaping one of the most complex maritime projects in EuropeSeabed consolidation works continue, along with the construction of the next caissons.
27 May 202622nt caisson installed for New Genoa BreakwaterCaisson installed just 3 days after the previous one Work ongoing 7 days a week on a project combining innovation and offshore operations
22 May 2026New Genoa Breakwater, 21st caisson installed A new milestone has been reached in the construction of the New Genoa Breakwater: the 21st caisson has been installed offshore the Ligurian port city. The project is being carried out by the PerGenova Breakwater Consortium, led by Webuild, on...
28 April 202620th caisson installed project reaches 900 metres in lengthConstruction of the New Genoa Breakwater continues with the installation of the 20th caisson.
31 March 2026Seventeenth caisson of New Genoa Breakwater installed Production of the protective armour blocks to safeguard the base of the structure has started The construction site of the New Genoa Breakwater marks another significant milestone with the installation of the 17th caisson by the PerGenova Breakwater consortium, led by Webuild, which is doing the project on behalf of the Western...